MUNICIPAL & PUBLIC WORKS |
 |
|

Top Bridge Pedestrian Crossing
| Location: |
|
Parksville, B.C. |
| |
|
|
| Scope: |
|
Construction of a two-span concrete and steel suspension bridge as a pedestrian crossing over the Englishman River. Constructed for Regional District of Nanaimo Parks and Recreation. |
| |
|
|
| Completed: |
|
2007 |

Port McNeill Reservoir
| Location: |
|
Port McNeill, B.C. |
| |
|
|
| Scope: |
|
Construction of a new reinforced concrete cell to the Port McNeill water reservoir. |
| |
|
|
| Completed: |
|
2008 |

Crown Isle Reservoir
| Location: |
|
Courtenay, B.C. |
| |
|
|
| Scope: |
|
Constructed for the Comox Valley Regional District, this is a 4 Million Litre glass lined bolted steel tank on a concrete foundation, completed with valve house and associated piping. |
| |
|
|
| Completed: |
|
2008 |

Arbutus Reservoir
| Location: |
|
Ladysmith, B.C. |
| |
|
|
| Scope: |
|
General Contractor for construction of a 33.0 metre diameter circular two-celled reinforced concrete reservoir (storage volume 5700 cubic metres). Fabrication, welding and installation of stainless steel reservoir inlet, outlet and drain piping including valves and fittings. |
| |
|
|
| Completed: |
|
2007 |

Beban Ice Arena
| Location: |
|
Nanaimo, B.C. |
| |
|
|
| Scope: |
|
General Contract for construction of ice arena. Intricate work involved to achieve close tolerance on concrete slab for ice surface. Included all concrete works, steel building, and interior and exterior finishes. |
| |
|
|
| Completed: |
|
1994 |

Beban Ice Arena 2
| Location: |
|
Nanaimo, B.C. |
| |
|
|
| Scope: |
|
General Contract for construction of ice arena. Intricate work involved to achieve close tolerance on concrete slab for ice surface. Included all concrete works, steel building, refrigeration, interior and exterior finishes, and mechanical and electrical work. |
| |
|
|
| Completed: |
|
1994 |

Ravensong Aquatic Centre, Qualicum Beach
| Location: |
|
Qualicum Beach |
| |
|
|
| Scope: |
|
General Contractor for construction of new aquatic center for Regional District of Nanaimo. Included main pool, wading pools, hot pool, change rooms, mechanical rooms and offices, and site services. |
| |
|
|
| Completed: |
|
1994 |

Swy-a-Lana Lagoon
| Location: |
|
Nanaimo Harbour, Nanaimo, B.C. |
| |
|
|
| Scope: |
|
Complete construction of civil works for lagoon in Maffeo-Sutton park including all earthworks, HDPE inlet pipe and valve, high quality cast-in-place decorative concrete works, tidal pools, and decorative railings. |
| |
|
|
| Completed: |
|
1984 |
|
|
|
|
 |
|
|
|